• Removed two layers of asphalt shingles
  • Replaced two rotten sheets of plywood with 1/2″ CDX
  • Applied Malarkey Highlander shingle line in Midnight Black
  • Removed all existing roofing including clean up with use of magnetic roller for nail pick up in driveways and yard
  • Installed 3” rigid insulation on entire roof deck
  • Installed 1/2 CDX plywood on top of rigid foam
  • Applied High temp ice and water-shield to entire roof surface
  • Installed Taylor Metal 26 gauge, MS-150, 16” Standing seam metal roofing panels on roof
  • Installed D metal on all eaves, included gable metal, roof to wall metal, ridge metal
  • Valley metal with butyl tape
  • Installed all new RVO bathroom vents and color matching if available pipe boots and color matching caulking
  • Removed and replaced chimney flashing. Saw cut into chimney and installed new flashing
  • Designed and ordered custom Z metal for chimney and applied for water-tight application
  • Aligned poly iso plates and screws with interior rafters to prevent exposure or nippling of screws through sheathing
  • Transported crew and planks to metal drop-off location to hand load and unload metal panels to job site
  • Removed all existing roofing
  • Applied synthetic underlayment to entire roof surface; ice and water shield in valleys and around penetrations
  • Applied metal to entire perimeter of roof
  • Removed and replaced existing ventilation with new ridge vent, also includes all new pipe boots.
  • Apply Malarkey 40 year Vista shingle product line in Storm Grey
  • Framed valley metal, ridge metal and step flashing with 1/2″ CDX plywood
  • Installed 60 Mil TPO as a cover over on top of carport. Includes new gable metal, fan fold thermal barrier & clad metal on eave
  • Installed 60 mil TPO in dead valley, remove siding and corner board and roll up the wall; re-installed siding
  • Welded gable seam to custom clad metal
  • Applied Malarkey 50 year Windsor XL shingle in Storm Grey
  • Remove old shingles and re-roof of main house and detached garage
  • Installed 60′ of baffled ridge vent per inspector report
  • Applied Malarkey Vista shingle product line in Midnight Black
  • Installed V300 ridge vent & roof jack vents per plan specifications
  • Roofed Community Building & Buildings 1,2,3 & 4
  • Applied Malarkey Vista product line in Natural Wood
  • Applied welded membrane on crickets to divert water
  • Removed all existing roofing, gutters and downspouts; cleaned grounds and dispose all debris
  • Applied synthetic underlayment to entire roof surface prior to roofing application and ice and water shield in valleys and around penetrations
  • Installed five new skylights 2’X4′ additional to existing, included framing, sheet rock installation, mud, tape texture and painting as well as flashing
  • Applied color matching granulated torch down or TPO membrane in dead valley section, included base sheet, step flashing and cap nails
  • Applied Malarkey’s Legacy 50 year product line
  • Installed all new 5″ white aluminum, seamless gutters and downspouts. Altered/redirected the existing downspout on the entry section per homeowners’ discretion
  • Temporarily staged plywood and tarps on deck to prevent damage during tear off.
  • Installed jacks and boards for roof loading and installation.
  • Removed all existing roofing, including any clean up with use of magnetic roller for nail pick up in driveways and yard.
  • Applied synthetic underlayment to entire roof surface with  ice and water shield in in valleys and around penetrations.
  • Applied metal to entire perimeter of roof.
  • Removed and replaced existing ventilation with new ridge vent and one RVO vent on back of home, also includes all new pipe boots.
  • Applied Malarkey 40 year Vista shingle product line in Storm Grey.